Summer of 2016 - Road Projects:
Project scheduled between July 25th to August 20th.
Eliot Street between the intersection of Pond Street to the intersection of Cedar Street - Mill and Overlay.
Thomas Road between the intersection of Dianne Lane and the intersection of Cordaville Road - Mill and Overlay.
Summer of 2015 - Road Projects:
- High St, Howe St, Tilton Ave and Concord Ave have street segments that were recently reclaimed and paved.
- Curb installation on Oak street from Kings row to the Oak street apartments and Frankland Rd to Rte 135 is complete.
- Myrtle St, Acton Rd had portion or all of the street repaired either through Mill and Overlay or just an Overlay. -Completed
- Cedar Street (from Eliot st to East Union) - Has been Milled and Paved.
LOAM AND SEED: Full Depth Reclaim Streets - High St and Concord Street have Loam and Seed on disturbed areas next to the pavement on various properties.
Driveway Berms -ONLY for driveways affected due to new pavement height have been installed.
Spring 2017:
- Chestnut Street (Portions)
- Main Street from Water Street to Homer Avenue - Work was postponed due to various factors.