Week ending January 12th, 2017.
The contractor has been informed by Eversource Gas that they are ready to install the gas line in the MBTA access road.
The plan is to commence work next Tuesday the 17th of January. The pipe material is already on site. The total job is expected to last about three weeks.
The Dow company were also scheduled to begin work next Tuesday on the sewer but that has been delayed due to survey control issues.
The contractor Reed Construction will be in touch with Ashland Police to secure the necessary details.
We will strive to stay out of the road between the hours of 8am and 4pm. This will allow us to miss some of the busiest trains (7:56 am inbound and 4:12pm, 5:11pm outbound).
The start time for the first day may need to be around 7:30am to allow our site contractor to open up some trench ahead of the gas company.