Work will start at 7 AM and could last until 5 PM on Monday and Tuesday
DOWNTOWN PROJECTS UPDATE (8/25/19) ** Homer Ave at Main Street **
Eversource (Devraux Construction) will be working on Homer Ave at Main Street on Monday and Tuesday.
Biszko will be starting to clean the water main on Main Street.
** Summer Street and Cherry Street **
This update is more specifically for the Summer Street Project. The following is planned for Monday and Tuesday next week:
1. Monday: Cherry Street will be closed at 7 AM. The closure will take place from Route 135 to Park Street near the Anne Marie's Dance Center. I do not expect Cherry Street to be closed all day. It should be opened up by noontime.
2. Monday (cont.) - Summer Street will be closed at 7 AM. The closure will take place from Park Road/Esty up to Cherry Street. I am expecting this section to be closed all day up until about 5 PM.
3. Tuesday - Summer Street will be closed at 7 AM. The closure will take place from Park Road/Esty up to Cherry Street. I am expecting this section to be closed all day up until about 5 PM.
An update will be sent out updating the project on Monday or Tuesday when we have a better idea what the rest of the week will look like.
DOWNTOWN PROJECTS UPDATE (8/21/19)
The following is an update on the three projects currently underway downtown:
Main Street Water Main Cleaning and Lining
Project 1: The Contractor (Biszko) is in the process of chlorinating and testing the water bypass and connecting water services. Hopefully, the Contractor will be able to make substantial progress next week.
Summer Street Water Main Replacement
Project 2: In order to minimize traffic impacts when the buses start running when school starts on September 3rd, the following work is planned for Summer Street which will impact Cherry Street as well. The updates will be posted more periodically in order to help you plan your commute throughout the next several weeks.
Thursday (8/22) and Friday (8/23)
The Contractor, A.Vozzella and Sons, will start pipe installation this week off the road at the end of Summer Street at Cherry Street.
Next week (8/26 – 8/30)
** TEMPORARY ROAD CLOSURES EXPECTED – CHERRY STREET AND SUMMER STREET **
Monday: Cherry Street Closed (7 AM to noontime)
Monday: Summer Street Closed (7 AM to 4 PM)
Tuesday: Summer Street Closed (7 AM to 4 PM)
Wednesday: Summer Street Closed (7 AM to 4 PM)
Thursday: TBA
Friday: TBA
Police Details will be in place to help assist.
Homer Ave. – Gas Main Installation
Eversource is making fast progress on Homer Ave. There is a good chance that they will be done with the phase of the project by the end of next week.
Thank you all for your patience.
Downtown Projects - Update 8/16/19
Main street: Contractor is in the bacteria testing phase of the project. Once all samples pass the bacteria testing they will start switching over buildings to the temporary water main. We are waiting for the results of the samples taken this morning. The results should be available Monday or Tuesday.
Summer Street: Contractor has completed the temporary water pipe installation and has taken water samples. We are expecting results back early next week. Once the temporary water pipe bacteria samples pass the testing the contractor will begin switching houses over to the temporary pipe. Once that is completed they will begin the water main replacement work. Contractor has started installation of side street gate valves to allow the new water main installation.
Homer Ave. – Gas Main Installation – Eversource Energy started their project on Friday, 8/9/19. They are installing a new gas main down Homer Ave. (from Main Street to Alden Street). One lane will be open to traffic. We expect this project to take up to 4 weeks.
Thank you for your patience.
Downtown Projects – Update 8/9/19
Project 1 (Main Street Water Main Cleaning and Lining) – The Contractor, Biszko, will be disinfecting the temporary water main along with some possible pit excavation. Beyond that, no other work until the bypass pipe passed the water test. There is a small chance that the Contractor will be able to start switching over the water services to the temporary water main at the end of the week.
Project 2 (Summer Street Water Main Replacement) – The Contractor, A.Vozzella, will be installing new valves in the existing water main on Park Street, Esty Street, and Cherry Street. If necessary, Linden Street will receive a new water valve as well. Water service will be temporarily interrupted during this work.
The tentative shut down schedule for Vozzella next week is:
Monday, Park St
Tuesday, Esty St
Wednesday, Cherry St
Thursday, Linden if needed
Project 3 (Homer Ave. – Gas Main Installation) – Eversource Energy started their project on Friday, 8/9/19. They will be working on Saturday, 8/10/19 as well. They are installing a new gas main down Homer Ave. (from Main Street to Alden Street). One lane will be open to traffic. We expect this project to take up to 4 weeks.
All three projects involve construction in the intersection of Summer/Main Street. We are trying to have most of the work completed in this intersection before September 3, when School starts back up.
Downtown Water Project Update: 8/2/19
The Main Street Water Main Contractor, Biszko, finished installing by-pass piping for the Main Street project last week and started the disinfection process.
The Summer Street Contractor, Vozzello, will mobilize Monday, 8-5-19, and start excavating pits on Tuesday, in Main Street for Biszko, starting at Summer Street.
Biszko will assist Vozzello and begin the Summer Street temporary by-pass piping, starting Tuesday or Wednesday and continuing into Thursday.
Biszko may begin water pipe cleaning and lining on Main Street during the week of 8-12-19.
Downtown Water Project Update: 7-30-19
(Tuesday morning) The Summer Street westbound travel lane will be temporarily closed for approximately 2 hours starting at 9 AM. Westbound traffic will be detoured down Main Street to Route 135 near Materese Funeral Home. Traffic traveling down Summer Street towards downtown will not be detoured.
Thank you for your patience.
Previously posted:
1. Main Street Water Main Cleaning and Lining
For the upcoming workweek (7/29 - 8/2): The Contractor, Biszko Contracting Corp., will be finishing the water bypass installation in and around downtown. When the installation is complete, the bypass will be filled with water and tested.
Next week (8/5 - 8/9), Biszko will start connecting the water services to the commercial establishments, residential units and town building along Main Street. Roadway construction should start that week.
2. Summer Street Water Main Replacement
Summer Street will also need a temporary water main bypass. This work should start within the next two weeks.
Overall, the impacts to the traffic will be minimal on Main Street and Summer Street at this time. If you have any questions, please contact Dan Maurer at dmaurer@ashlandmass.com.
Thank you,
The Department of Public Works